Complete Job

 

In some cases, a job may need to be taken through its final stage to continue a job stream and indicate to the system that it has completed. The job's command list is not processed, nor are any resource or end action list commands.  The job will appear as a successful completion in the P (Holding previous completions) queue and initiates will be submitted if they are used in combination. If the command is used to recover from a previous job run, the set id of the previous run should be designated to insure proper job flow.

 

When a job is submitted manually, the user is prompted for a number of final options that may be applied to the submission. These options may be left as the default or changed to customize job submission.

The completion options are:

 

Job set identity

Indicates to what set the job belongs. If a number is not provided then the system automatically assigns the next available set number.

Tag Data

Specifies information to be passed from one job to another inside a set of jobs.

Runtime Parameters

Specifies information to be passed from one job to another inside a set of jobs.

Initiate Checkbox

Indicates whether or not on completion of the job, the initiate list should be carried out.

Step number to finish with

indicates at which step to finish the job.

Status Code Upon Completion

An odd number indicates success and an even number indicates failure